CNR International (U.K.) Limited
 
 
 

Decommissioning Programme

CNR International’s plans to decommission the Ninian Northern Platform began in 2016, involving extensive engagement with stakeholders and many in-depth studies. These enabled a well-informed Comparative Assessment of decommissioning options to be carried out and a full Environmental Impact Assessment to be prepared. These, together with other relevant documents, are available from the Documentation Library.

Consultation on the Draft Decommissioning Programme was conducted in March and April 2017, prior to the plans being considered by OSPAR.

Regulatory approval of the Final Decommissioning Programme was granted in 2019.

 

 

Page updated 6-06-2024
Privacy
Reference material and supporting documents Decommissioning Programme Comparative Assessment Report Environmental Statement Stakeholder Consultation Report Independent Review Report